On the third day of Christmas ASME gave to me 
A means to detect floods per 2.2.9


This code change only pertains to buildings where the elevator can travel below the flood elevation for the property. If that's the case, flood detection must be provided between 6" and 12" above the finished floor (AFF). How the elevator responds to the detection of water is governed by section 2.27.13.

If you have any questions regarding your specific situation, be sure to contact us.