Existing elevator & project scope – The building owner had a few issues with the elevator system and we had prepared them over the years that the day was coming where they would have to replace the equipment, the day finally came.
New equipment providers
Controllers – Smartrise Engineering
Power
units – Delaware Elevator w/Maxton UC4 valve
Door
operators – GAL MOVFR
Fixtures
– Innovation Industries
Hydraulic elevator controller – The 1969 Elevator Research and Manufacturing[ERM] had seen its better days and was ready for replacement. Some minor replacements had been made over the years; a new electronic selector and a new starter.
Hydraulic elevator power unit – This was a Colley Elevator special, made in Franklin Park, IL.
Elevator fixtures – The old EPCO
fixtures are replaced with new code compliant Innovation Industries elevator
fixtures.
Take away – The elevator
modernization is a pretty vanilla one in the grand scheme of things. But, this is what most elevator
modernizations are, buildings with older elevator equipment who need to be
educated prior to their elevator equipment conking out. It is amazing to see some of the equipment we
installed back in the late 1960’s still running. I was just at a building in Skokie, IL that still
has a 1966 Colley Elevator running. I’m
confident that the elevators we are currently installing, as an industry, will not last close to 52 years. Way to go 1969 Team Colley. The Chicago Cubs are still here, Colley Elevator is still here. We have some legends on both teams.
Hey! Sign up for our mailing list! We should be getting a monthly email going out sometime in Q1 of next year.
If you have any questions or would like additional information feel free to contact me at CraigZ@colleyelevator.com or 630-766-7230 ext. 107.
Also check us out on Instagram @Colleyelevator see what we have been up to.
No comments:
Post a Comment