Saturday, June 22, 2019

Guide for elevator new construction for general contractors and building owners


This is meant to be a guide for general contractors when working with an elevator contractor for a new installation.  We work with GC’s or CM’s that have a variety of experience doing elevators from doing them on a regular basis to being their first one.

[As contractors we look forward to the day we have a truck onsite]

1st rule – Do not building your elevator hoistway without final drawings – Under no circumstance should anyone building a hoist way without a final drawing.  All elevator systems are not the same.  The mason will need to install connection devices[inserts, tube steel, etc] in certain places in the hoistway.  The most important thing is you may not build the hoistway for the elevator you ultimately purchase so it would go from a vanilla installation price to a custom price because the company you hired doesn’t use the same foot print.  I.E. use a Kone MRL foot print and end up deciding not to work with Kone, If you building the hoistway for the Kone elevator, you may have a huge problem with additional costs.

If you are not familiar with elevator drawings have the elevator contractor come out and walk you through what you need.  We are not building a rocket ship but we are building something that requires many different trades to work together.

Hoistway entrances – Pay attention to the rough opening we will need and keep the entrance that we will be installing the cab in open so we can get the platform in.

[Wonderful! The 1st landing HW entrance is open]


Hoistway inserts/connections – Make sure you know where to put them in the hoist way.  As a GC or CM, you may know but whomever is going to be installing them should also have a good understanding before they begin constructing the hoistway.  On construction sites I get a lot of “yeah I do this all the time” and people shaking their heads and we still have inserts installed in the wrong place. If you have alternate means of connecting the rails to the hoistway work with your contractor on a solution, do not assume it will work because the architect/design team said it will.

[Typical wall insert in CMU]


[This building is using tube steel instead of CMU inserts]

 Have the elevator pit ready to go – Make sure your pit is 48” or 60” or whatever it says on the drawings.  You will also need a sump pump that can pump 3000ga per hour, have the hole in.  If you have questions on where it goes, call your elevator contractor for direction and do not put it where you think it should go, put it where the elevator contractor tells you or where the drawings show.  We have items that go in the pit that are need to go in a certain spot.  Priority 1 is an elevator installation not making life easy for the concrete guy or the plumber.

[A prepreconstruction site visit to meet the CM/GC - Pit is getting ready]

[Pit ended up beautiful]

[A recent site visit when a GC told me the hoisway/pit was ready]


Main line power – When you expect the elevator contractor to start, make sure you have main line power and lights in the elevator room.  Please do not tell us you have power when you do not, we will come out and work for 8 hours and then tell you to call us back when you have power and most companies charge you with a remobilization charge.  Lights in the machine room are important as well.  Know your electrical clearances and where the elevator equipment will be placed before installing the disconnects.


110vac power in pit and machine room – Our tools need to plug into something it is helpful when we have live power in the machine room and our pit so we can avoid stringing extension cords all over your building.


Environmental controls – We love environmental controls HVAC!  Be aware when these are being installed the #1 priority is elevator installation not making life easier for the HVAC guy.  We have a controller and machine that needs to be placed somewhere if we have a machine room.  In picture we see we have this wonderful air conditioner with water pipes everywhere.  We do not want water pipes in our machine room.

[Love the HVAC, don't love the water pipes]

Phone line – Get your phone line ready.  You can use a POTs line, VOIP, Cellular or whatever.  When we start have it waiting and have it be live!  We don’t want to get to the end of the project and not be able to get the elevator inspection because there is no 2 way communication.

Hoist beam – If you want to make friends with your elevator project crew put the beam where it is supposed to be on the drawings.  This will make the project go faster and safer.

[This beam is very important to us when doing our installation]

Staging & delivery- clear out a space for the elevator contractor so when he starts he has a clear and safe space.  Also please have means to have our large and heavy equipment to be unloaded.

[Not a great staging area]

[We appreciate it when we have a clear means to deliver equipment - This construction site did not have a clear means for us to get material in the building]

Trade meeting – Get the trades together to discuss their scopes and have them ask questions and go over drawings. The meeting is not about the vanity of the general contractor, building owner or elevator contractor it is about the successful installation of a conveyance system that requires all parties to do their part.

[This was a construction meeting that included all trades involved]

Before approving drawings understand what is mentioned on the lay out drawings.  No matter how many elevators you have installed please read what is on the new installation front page.

Hoistway and pit
1.    A clear hoistway to the dimensions on the drawing, plumb within ½” to 1” total.  Hoistway shown is minimum.  Any out of plumb condition must not encroach on hoistway size envelope from top to bottom
2.    Venting of hoistway as required by code
3.    A dry pit reinforced to sustain vertical loads as shown.

4.    A pit ladder for each elevator of non combustible material, constructed and installed in accordance with code, and extending from pit floor to 48” above sill of lowest hoistway door.
5.    Adequate supports for guide rail brackets, to support horizontal loads as shown.  Support locations must not exceed spacing as required by code, and as shown.  When maximum spacing is exceeded, rail reinforcement, or added supports must be provided at purchaser’s expense.
6.    Guide rail support location must be steel, brick, concrete, or filled concrete block.  Inserts, if used, are supplied and installed by others, in locations shown, as walls are erected.  If rail brackets are attached to steel beams, fire proofing is to be applied after rail brackets are installed.
7.    Permanent provisions shall be made to prevent accumulation of water in hoistway pit per ASME A17.1
8.    Projections or recesses in hoistway of 4” or more, on sides not used for loading or unloading, shall be beveled at an angle not less than 75 degrees from the horizontal.
9.    A hoist beam, book or eyebolt shall be furnished at the top of hoisway located on centerline of car and guides – designed for load capacity of 6000lbs minimum.
10. Entrance walls accepting passenger type entrances are to be erected(or rough opening as shown filled in] after door frames and sills are installed
11. A suitable sill support and recess as shown, full width of hoistway, grouted by others after door sills are installed.
12. Required sleeves in hoistway walls, or any trenching and filling, for oil line and wire duct for each elevator, as shown.
13. Any cutting and patching of building construction required to install signal fixtures or other elevator apparatus and any repairs, grouting, patching or painting made necessary by same
14. Barricades may be required during construction – hoistway protection
15. Hoistway shall have means to maintain temperature between 40 degrees and 105 degrees

Control Space
16. A properly lit and ventilated control space per code requirements, with temperature maintained between 55 degrees and 90 degrees.  Door size show to permit access for machine.
17. Machine room to be designed and laid out to comply with electrical clearance requirements and maintenance clearance requirements.  Elevator contractor’s equipment is priority here not the plumber, HVAC, electrician, security or fire alarm equipment.  If their equipment is in the way, they will need to move it.

Electrical & pit – All electrical in accordance with ASME and NEC
18. A fused disconnect switch for each elevator, of ample capacity, wirth wiring to the elevator motor starter control.  Disconnecting means shall disconnect the normal power supply as well as emergency supply, when provided.
19. Light and switch in elevator control space, with switch located adjacent ot the access door.  Convenience outlet in control space[GFI].
20. Light, switch and convenience outlet in elevator pit, light switch accessible from lower landing opening.  Install light to clear elevator car.
21. Suitable 110v service in the hoistway, midway of travel[see layout] or connected to terminals in elevator controller for car light service[elevator contractor option]
22. Heat, and product combustion sensors located in each elevator lobby with necessary wiring to elevator control panel, when fire service is required
23. If sprinklers are present in the control space or hoistway, a means shall be provided to automatically disconnect the mainline power supply prior to the application of wire[shunt trip].
24. All items shall conform to local building code
25. Relative humidity not to exceed 85%

Take away - If we all work together and follow the general guide lines given by a good/competent elevator contractor/new construction team we can go from a muddy construction site to a beautiful lobby with running elevators.

[beginning]

[End]

If you have any questions or would like additional information feel free to contact me at CraigZ@colleyelevator.com or 630-766-7230 ext. 107.

Also check us out on Instagram @Colleyelevator see what we have been up to.

7 comments:

  1. As one of the leading web design agency , A DataIT Solutions is understand that every client has a unique set of requirements that can be in the form of either generating leads, increasing sales or boosting traffic.
    Elevator Contractor Website Design | Moving Walkways Website Design

    ReplyDelete
  2. At DataIT Solutions, we love to create! Our dedicated team of specialists are always thinking outside the box to produce refreshing ideas to help your business stand out from the crowd.
     Excavation Work Contractor Website Design

    ReplyDelete
  3. Thanks for sharing such an informative post.

    ReplyDelete


  4. Hiring someone to return bent your home and fix your home shouldn't be a hassle. once you call a handyman to return out and perform handyman services you expect they show up once they say they're going to , do what they assert they're going to do and return your calls once you have questions before or after the work is completed . it's important that you simply realize once you are hiring a handyman his services are mostly general maintenance projects and not full blown renovations. If you're trying to find someone to redo the entire bathroom you'll call a contractor who focuses on bathroom remodeling. If you're looking to possess the tap replaced you turn a handyman's services.
    Toledo handyman

    ReplyDelete
  5. We are professional Movers and packers company in Dubai. We provide best packing and
    Movers in Dubai

    ReplyDelete