This
traction freight elevator modernization project took an entire team to
complete; from the building owner design team, general contractor, electrician, fire recall company, security company, sales people, engineering, 4 different major equipment suppliers, field support, IUEC elevator constructors. 2 years in
the making the project is finally completed.
Many thanks to everyone involved especially the installers!
The
background on this elevator is that it was a Montgomery Elevator installed in
1940’s sometime and it had manual door operation with bi parting freight doors
on the front and swing doors on the dock.
The specification called for making it an automatic freight car with new
everything except the rails.
Controller
– MCE
Machine,
sling, safeties, HW equipment – Hollister Whitney
Cab
& doors – EMS
Fixtures
– Innovation
Machine
– Holliser Whitney – A geared application was specified on this project, it was
identified that not only would it be a tight fit to get this machine in, it
also needed additional structural supports as the small foot print of the
Montgomery machine had different reaction points and requirements. Adding the weight of the new sling, platform
and automatic gates required more steel to be installed in the elevator room.
[Old small foot print Montgomery machine]
[Old small foot print Montgomery machine]
[New gearless HWEC machine]
Controller
– MCE was chosen to do this project because they used one less electrical
device/box for incoming power. The
machine room is very small so space was at a premium. Some of the other manufacturers qualified for
this specification had and additional device/box.
Hoistway
doors – EMS – We had some significant challenges on this project as the
hoistway was fire block and there wasn’t a lot of material to work with to
attach the new doors to. The team
working on the project did a beautiful job working with the existing conditions
to make it work.
Cab – EMS – New automatic gates replaced the manual wood gates.
[Old swing doors on dock side - Interior]
[Old swing doors on dock side - Exterior]
[New dock side bi parting automatic freight doors]
[Typical manual freight doors at each landing]
[New automatic freight doors at each landing]
Cab – EMS – New automatic gates replaced the manual wood gates.
Fixtures
– Innovation – New fixtures installed.
When pictures where taken we were still doing a final clean down of
finger prints.
[Old Montgomery fixtures]
[New Innovation fixtures]
Pit
work – Hollister Whitney – The pit was discovered during engineering to need to
be re-poured and re-enforced. The pit
was shallow to begin with so every inch counted with the excavation and
re-pour.
[Old pit]
[New pit]
This
was a challenging project for everyone involved and it turned out great. From the initial hiccups of having the need
for more design work after the initial specifications could not be met with the
existing conditions to the completion there was over 40 people who worked on
this project; building owner design team, general contractor, electrician, fire recall company, security company, sales people, engineering, 4
different major equipment suppliers, field support, IUEC elevator constructors.
Hats off to our IUEC constructors who made each challenge a reality and
Hollister Whitney’s engineering for having patience and knowledge to find structural
solutions to make this a reality.
As
always feel free to contact us at www.colleyelevator.com,
email Craigz@colleyelevator.com or call 630-766-7230.
No comments:
Post a Comment